Minister of Works Dave Umahi has allayed fears raised by motorists and observers about water pooling on the Lagos-Calabar Coastal Highway, confirming that the project and other key federal road schemes remain on track for completion by 2031.
Speaking Friday after an inspection of sections one and two alongside lawmakers, Umahi responded to criticism about flooding and depressions on the corridor. He clarified that the water seen along the median results from the design’s future railway provision, not a defect.
“The median area spans about 25 meters—essentially another dual carriageway—and was meant for trains,” he explained. Since railway work has not begun, the contractor has been instructed to install drainage within the median and link it to the existing system.
Umahi acknowledged minor depressions may collect rainwater but said corrective actions are underway. “I take responsibility for those slight depressions, and we are fixing them. There is no need for worry,” he stressed.
He rejected speculation that the coastal road might be abandoned, noting significant progress in just two years: “Section one, 47 kilometers with six lanes, is complete—ahead of its three-year timeline. Section two, 55 kilometers, will be largely finished by November.”
Work is advancing on sections three and four in Cross River, Akwa Ibom, Ogun, and Ondo states. Umahi noted that challenging terrain and environmental rules have required redesigns and route adjustments. “Engineering adapts. In some protected forest areas, international regulations block construction, so we create alternative alignments,” he said.
He praised Hitech Construction for continuing work despite delayed payments, calling it a true partnership. “Few companies show such commitment under these circumstances.”
Umahi also reported progress on the Sokoto-Badagry Super Highway and other major roads in Kebbi, Oyo, Gombe, and Akwa Ibom. He reaffirmed that all four legacy projects under President Bola Tinubu will meet their 2031 deadline. “These projects will be completed on time. We have reputable contractors like Hitech, Infouest, and CGC,” he concluded.